Electricity Distribution Improvements

HRPF followed electricity-distribution proposals with GEPCO and oversight authorities, supporting approval and delivery of transformer, pole and cable improvements in Mianwal Ranjha.

Mianwal Ranjha, Mandi BahauddinElectricity infrastructure advocacy recorded in 2023–2025Residents affected by overloading and distribution problems

In pictures

HRPF presenting appreciation to GEPCO officials
1 / 3

About this project

HRPF followed electricity-distribution proposals with GEPCO and oversight authorities, supporting approval and delivery of transformer, pole and cable improvements in Mianwal Ranjha.

The challenge

Overloading and distribution problems affected local electricity supply and required coordinated infrastructure action.

Our approach

HRPF raised unresolved proposals with the Power Division, GEPCO and the Federal Ombudsman and followed implementation by the electricity provider.

What we aim to achieve

  • Seek improvements to overloaded electricity-distribution infrastructure.

What we do

  • Raised distribution and overloading concerns.
  • Followed HT/LT proposals with GEPCO and oversight authorities.
  • Pursued remaining infrastructure work.
  • Followed up approved LT/HT proposals and requested the materials needed for implementation.

Results and lasting change

  • Approval and implementation of several infrastructure proposals were recorded.
  • The 2025 account describes completed work alongside remaining items under follow-up.

From plans to progress

Project timeline

  1. 18 July 2023

    Materials requested for approved proposals

    HRPF requested release of materials for approved LT/HT proposals in the Mianwal Ranjha feeder area.